School nameMSBAIDProject TypeProject PhaseTotal Project BudgetReimbursement RateEstimated Building Completion DateMSBA Amt Paid(to Date)Estimated MSBA Payment Amt Remaining
Ashland Middle201300140405Accelerated RepairFinal Audit Approved$3,325,39650.16% $903,881 
David Mindess200900140015GGreen RepairFinal Audit Approved$2,384,02148.68% August, 2010 $1,031,429 
David Mindess201700140015Core ProgramBuilding Complete$84,637,00055.57% July, 2023 $28,659,713$3,282,301
Henry E Warren Elementary201300140010Accelerated RepairFinal Audit Approved$2,433,42650.16% $606,140 
Notice on MSBA Project Information
The MSBA updates the project information on the MSBA website on a regular basis; however, due to timing issues or other circumstances, there may be instances where the most up-to-date information does not yet appear. If you have questions or concerns about any of the project information, please contact the MSBA.
The Estimated MSBA Payment Amount Remaining is the maximum amount of funding that the District may still receive from the MSBA for the Project. The actual amount paid by the MSBA may equal an amount less than this estimated amount, as determined by an audit conducted by the MSBA.