Selected District: Boston
Total Number of Projects: 45 Number of Active Projects: 7

List of Projects for the District are as follows:

School nameMSBAIDProject TypeProject PhaseTotal Project BudgetReimbursement RateEstimated Building Completion DateMSBA Amt Paid(to Date)Estimated MSBA Payment Amt Remaining
Boston Arts Academy201300350546Core ProgramBuilding Complete$137,370,91670.36% May, 2022 $35,944,448$12,242,127
Boston Day and Evening Academy202100350505Accelerated RepairDesign Development$7,286,31560.42% $89,567$4,081,055
Boston Latin201600350560Accelerated RepairCloseout$2,182,66765.47% $968,941$199,213
Carter School201700350036Core ProgramConstruction$91,966,53264.31% August, 2025 $8,377,240$22,218,215
Charles Sumner201500350052Accelerated RepairFinal Audit Approved$2,562,60665.47% August, 2017 $1,445,910 
Charles Sumner201700350052Accelerated RepairCloseout$1,370,38165.47% $717,399$78,993
Clarence R Edwards Middle201100350430GGreen RepairFinal Audit Approved$1,738,81474.06% $769,046 
Curley K-8 School201500350020Accelerated RepairFinal Audit Approved$5,021,27465.47% August, 2017 $2,587,219 
Curley K-8 School201900350020Accelerated RepairCloseout$1,674,84562.52% August, 2021 $655,407$68,837
David A Ellis201500350072Accelerated RepairFinal Audit Approved$3,851,60365.47% August, 2017 $2,251,116 
Donald Mckay201500350080Accelerated RepairFinal Audit Approved$3,436,53565.47% August, 2017 $1,909,440 
Donald Mckay201800350080Accelerated RepairCloseout$1,604,67061.89% $844,588$84,604
Dorchester Academy201500350651Accelerated RepairFinal Audit Approved$4,998,62465.47% August, 2017 $3,108,841 
Dr. William Henderson Upper202100350426Accelerated RepairDesign Development$4,527,98760.42% $99,580$2,489,073
East Boston High201700350530Accelerated RepairCloseout$2,865,98065.47% $1,475,860$163,364
Excel High School201100350522GGreen RepairFinal Audit Approved$1,227,18074.06% $878,610 
Grover Cleveland200800350415Core ProgramN/A     
Grover Cleveland201500350415Accelerated RepairFinal Audit Approved$2,838,36265.47% August, 2017 $1,417,526 
Henry Dearborn Middle School201000350074Core ProgramFinal Audit Approved$73,275,77875.34% February, 2018 $35,705,878 
Hugh Roe O'Donnell201700350141Accelerated RepairCloseout$1,256,74465.47% $675,978$94,627
James Condon Elementary201600350146Accelerated RepairCloseout$2,260,97865.47% $527,665$168,296
James Otis201800350156Accelerated RepairCloseout$2,496,64761.89% $1,231,228$237,407
James P Timilty Middle201700350485Accelerated RepairN/A     
Jeremiah E Burke HighW20034222WaitlistFinal Audit Approved$49,500,00090.00% March, 2009 $40,731,964 
John Marshall201700350178Accelerated RepairCloseout$5,429,30465.47% $2,735,396$348,189
John W McCormack201600350179Accelerated RepairCloseout$2,091,70065.47% $1,202,557$166,879
Joseph Lee201100350183GGreen RepairFinal Audit Approved$2,149,15674.06% $1,334,953 
Josiah Quincy201800350286Accelerated RepairCloseout$1,873,09861.89% $890,842$110,721
Lyndon201800350262Accelerated RepairCloseout$1,938,04661.89% $1,011,361$128,966
Lyon Upper 9-12201900350655Accelerated RepairCloseout$1,942,10262.52% August, 2021 $760,127$84,532
Maurice J Tobin201700350229Accelerated RepairCloseout$1,907,14665.47% $803,307$115,508
O'Bryant School Math/Science201800350575Accelerated RepairCloseout$1,583,28661.89% $758,439$169,740
Patrick J Kennedy202000350264Accelerated RepairFinal Audit Approved$237,88561.05% $50,208 
Paul A Dever201600350268Accelerated RepairCloseout$1,897,39165.47% $1,097,681$144,541
Quincy Upper School201000350565Core ProgramConstruction$223,891,46765.94% June, 2024 $36,801,390$25,784,374
Rafael Hernandez201800350691Accelerated RepairCloseout$1,440,67261.89% $757,712$81,801
Rafael Hernandez202100350691Accelerated RepairDesign Development$6,420,01660.42% $87,069$3,452,623
Samuel Adams202000350302Accelerated RepairFinal Audit Approved$289,49561.05% $80,385 
Thomas A Edison Jr High201100350425GGreen RepairFinal Audit Approved$3,734,22974.06% $2,027,760 
Washington Irving Middle201100350445GGreen RepairFinal Audit Approved$1,400,86674.06% $918,106 
William E Russell201700350366Accelerated RepairCloseout$2,086,26065.47% $990,357$108,992
William E Russell202100350366Accelerated RepairDesign Development$4,346,22860.42% $133,114$2,307,757
William Ellery Channing201600350360Accelerated RepairCloseout$1,369,44465.47% $518,897$95,445
William McKinley201900350363Accelerated RepairCloseout$3,433,66062.52% June, 2021 $1,484,179$154,789
Young Achievers201500350380Accelerated RepairFinal Audit Approved$5,152,72065.47% August, 2017 $2,582,833 
Notice on MSBA Project Information
The MSBA updates the project information on the MSBA website on a regular basis; however, due to timing issues or other circumstances, there may be instances where the most up-to-date information does not yet appear. If you have questions or concerns about any of the project information, please contact the MSBA.
The Estimated MSBA Payment Amount Remaining is the maximum amount of funding that the District may still receive from the MSBA for the Project. The actual amount paid by the MSBA may equal an amount less than this estimated amount, as determined by an audit conducted by the MSBA.