School nameMSBAIDProject TypeProject PhaseTotal Project BudgetReimbursement RateEstimated Building Completion DateMSBA Amt Paid(to Date)Estimated MSBA Payment Amt Remaining
Cambridge Rindge and LatinW20024323WaitlistFinal Audit Approved$29,721,67064.28% $9,021,670 
Cambridge Rindge and LatinW20034382WaitlistFinal Audit Approved$112,116,30069.47% $28,026,977 
Cambridgeport202000490007Accelerated RepairConstruction$2,242,10046.12% August, 2022 $748,517$95,053
Fletcher/Maynard Academy201500490090Accelerated RepairFinal Audit Approved$958,89347.03% $371,366 
Fletcher/Maynard Academy201600490090Accelerated RepairCloseout$1,057,52336.99% $271,582$58,299
Graham and Parks201800490080Accelerated RepairFinal Audit Approved$2,950,22245.49% December, 2019 $1,155,148 
Kennedy-Longfellow201500490040Accelerated RepairFinal Audit Approved$3,264,96847.03% $645,859 
Notice on MSBA Project Information
The MSBA updates the project information on the MSBA website on a regular basis; however, due to timing issues or other circumstances, there may be instances where the most up-to-date information does not yet appear. If you have questions or concerns about any of the project information, please contact the MSBA.
The Estimated MSBA Payment Amount Remaining is the maximum amount of funding that the District may still receive from the MSBA for the Project. The actual amount paid by the MSBA may equal an amount less than this estimated amount, as determined by an audit conducted by the MSBA.