School nameMSBAIDProject TypeProject PhaseTotal Project BudgetReimbursement RateEstimated Building Completion DateMSBA Amt Paid(to Date)Estimated MSBA Payment Amt Remaining
Breed Middle School201201630405Accelerated RepairFinal Audit Approved$2,557,32480.00% $1,651,402 
Capt William G Shoemaker202101630090Accelerated RepairConstruction$3,372,50079.58%  $2,455,300
E J Harrington201401630045Accelerated RepairFinal Audit Approved$1,863,43178.95% $1,106,870 
Hood201701630055Accelerated RepairFinal Audit Approved$5,882,19379.58% April, 2019 $3,255,859 
Lynn Vocational Technical Institute201201630605Accelerated RepairFinal Audit Approved$3,741,08780.00% $2,778,712 
Lynn Vocational Technical Institute201801630605Accelerated RepairCloseout$4,237,78879.58% $1,508,626$546,288
Lynn Vocational Technical Institute202001630605Accelerated RepairConstruction$11,289,82578.95% December, 2023 $6,202,159$1,911,762
Pickering Middle201401630420Core ProgramFinal Audit Approved$1,105,00079.58% $789,278 
Pickering Middle202001630420Core ProgramDesign Development$1,510,00079.58%   
Thurgood Marshall Mid200901630305Core ProgramFinal Audit Approved$92,000,00080.00% $49,075,316 
Wm P Connery201401630040Accelerated RepairFinal Audit Approved$1,101,40278.95% $597,541 
Notice on MSBA Project Information
The MSBA updates the project information on the MSBA website on a regular basis; however, due to timing issues or other circumstances, there may be instances where the most up-to-date information does not yet appear. If you have questions or concerns about any of the project information, please contact the MSBA.
The Estimated MSBA Payment Amount Remaining is the maximum amount of funding that the District may still receive from the MSBA for the Project. The actual amount paid by the MSBA may equal an amount less than this estimated amount, as determined by an audit conducted by the MSBA.