Selected District: North Attleborough
Total Number of Projects: 6 Number of Active Projects: 1

List of Projects for the District are as follows:

School nameMSBAIDProject TypeProject PhaseTotal Project BudgetReimbursement RateEstimated Building Completion DateMSBA Amt Paid(to Date)Estimated MSBA Payment Amt Remaining
Falls201102120010GGreen RepairFinal Audit Approved$701,26352.06% $344,616 
Joseph W Martin Jr Elementary200902120013GGreen RepairFinal Audit Approved$633,36552.06% $320,123 
North Attleboro High201202120505Science Lab InitiativeFinal Audit Approved$6,101,81152.06% $2,978,748 
North Attleboro High202102120505Core ProgramFeasibility Study$2,000,00055.63%  $1,112,600
Roosevelt Avenue201202120015Accelerated RepairFinal Audit Approved$997,00052.06% $437,750 
Roosevelt Avenue201402120015Accelerated RepairFinal Audit Approved$400,00053.53% $181,568 
Notice on MSBA Project Information
The MSBA updates the project information on the MSBA website on a regular basis; however, due to timing issues or other circumstances, there may be instances where the most up-to-date information does not yet appear. If you have questions or concerns about any of the project information, please contact the MSBA.
The Estimated MSBA Payment Amount Remaining is the maximum amount of funding that the District may still receive from the MSBA for the Project. The actual amount paid by the MSBA may equal an amount less than this estimated amount, as determined by an audit conducted by the MSBA.