School Districts Cities And Towns
 Print this Page
Selected District: Braintree
Total Number of Projects: 12 Number of Active Projects: 1

List of Projects for the District are as follows:

School nameMSBAIDProject TypeProject PhaseTotal Project BudgetReimbursement RateEstimated Building Completion DateMSBA Amt Paid(to Date)Estimated MSBA Payment Amt Remaining
Archie T Morrison201000400033GGreen RepairFinal Audit Approved$440,00048.47% $153,496 
Braintree High201000400505GGreen RepairFinal Audit Approved$441,70048.47% $203,739 
East Middle School201000400305GGreen RepairFinal Audit Approved$1,600,00048.47% $745,376 
East Middle School201300400305Core ProgramCloseout$82,607,81457.98% October, 2020 $37,428,173$3,842,142
Highlands201000400015GGreen RepairFinal Audit Approved$200,00048.47% $83,726 
Highlands202000400015Accelerated RepairCloseout$2,207,53150.58% $456,459$532,050
Hollis201000400005GGreen RepairFinal Audit Approved$660,00048.47% $254,176 
Hollis202100400005Accelerated RepairCloseout$4,811,82750.58% $839,106$205,382
Liberty202000400025Accelerated RepairCloseout$2,647,31750.58% $995,119$273,462
Mary E Flaherty School202100400020Accelerated RepairCloseout$4,530,85550.58% $880,973$468,415
South Middle School200800400310Core ProgramFinal Audit Approved$3,052,70248.47% $1,281,684 
South Middle School201600400310Core ProgramBuilding Complete$85,193,36553.96% August, 2023 $28,090,163$4,202,531
Notice on MSBA Project Information
The MSBA updates the project information on the MSBA website on a regular basis; however, due to timing issues or other circumstances, there may be instances where the most up-to-date information does not yet appear. If you have questions or concerns about any of the project information, please contact the MSBA.
The Estimated MSBA Payment Amount Remaining is the maximum amount of funding that the District may still receive from the MSBA for the Project. The actual amount paid by the MSBA may equal an amount less than this estimated amount, as determined by an audit conducted by the MSBA.