School Districts Cities And Towns
 Print this Page
Selected District: Haverhill
Total Number of Projects: 11 Number of Active Projects: 1

List of Projects for the District are as follows:

School nameMSBAIDProject TypeProject PhaseTotal Project BudgetReimbursement RateEstimated Building Completion DateMSBA Amt Paid(to Date)Estimated MSBA Payment Amt Remaining
Caleb Dustin Hunking201101280035GGreen RepairFinal Audit Approved$18,16971.91% $7,195 
Caleb Dustin Hunking201201280035Core ProgramFinal Audit Approved$61,379,37878.93% December, 2016 $39,892,131 
Consentino Middle School201101280100GGreen RepairFinal Audit Approved$1,780,14171.91% $1,191,782 
Consentino Middle School201801280100Core ProgramConstruction$159,944,15480.00% $11,050,848$90,783,867
Greenleaf Kindergarten Center201101280027GGreen RepairFinal Audit Approved$7,66971.91% $3,399 
Haverhill High202001280505Accelerated RepairFinal Audit Approved$1,079,02976.84% December, 2021 $626,054 
Haverhill HighW20034393WaitlistFinal Audit Approved     
John G Whittier201101280085GGreen RepairFinal Audit Approved$1,271,30371.91% $823,275 
Moody202101280045Accelerated RepairCloseout$511,15676.84%  $387,584
Tilton201101280075GGreen RepairFinal Audit Approved$900,95971.91% $572,830 
Walnut Square201101280080GGreen RepairFinal Audit Approved$1,007,35871.91% $497,756 
Notice on MSBA Project Information
The MSBA updates the project information on the MSBA website on a regular basis; however, due to timing issues or other circumstances, there may be instances where the most up-to-date information does not yet appear. If you have questions or concerns about any of the project information, please contact the MSBA.
The Estimated MSBA Payment Amount Remaining is the maximum amount of funding that the District may still receive from the MSBA for the Project. The actual amount paid by the MSBA may equal an amount less than this estimated amount, as determined by an audit conducted by the MSBA.