List of Projects for the District are as follows:

School nameMSBAIDProject TypeProject PhaseTotal Project BudgetReimbursement RateEstimated Building Completion DateMSBA Amt Paid(to Date)Estimated MSBA Payment Amt Remaining
Hingham Elementary School2008013101Core ProgramFinal Audit Approved$26,930,13340.00% September, 2009 $9,826,564 
Hingham Middle School201001310410Core ProgramFinal Audit Approved$58,414,48143.87% $23,553,895 
Plymouth River202001310019Accelerated RepairCloseout$3,993,60033.95% $940,422$109,502
Wm L Foster Elementary201901310010Core ProgramConstruction$113,335,74940.54% $19,056,468$9,532,510
Notice on MSBA Project Information
The MSBA updates the project information on the MSBA website on a regular basis; however, due to timing issues or other circumstances, there may be instances where the most up-to-date information does not yet appear. If you have questions or concerns about any of the project information, please contact the MSBA.
The Estimated MSBA Payment Amount Remaining is the maximum amount of funding that the District may still receive from the MSBA for the Project. The actual amount paid by the MSBA may equal an amount less than this estimated amount, as determined by an audit conducted by the MSBA.