School nameMSBAIDProject TypeProject PhaseTotal Project BudgetReimbursement RateEstimated Building Completion DateMSBA Amt Paid(to Date)Estimated MSBA Payment Amt Remaining
Arlington Elementary201701490008Accelerated RepairFinal Audit Approved$3,173,85680.00% November, 2018 $2,002,759 
Francis M Leahy201701490040Core ProgramConstruction$115,795,79780.00% May, 2025 $37,518,397$28,724,610
Henry K Oliver201601490050Core ProgramConstruction$147,800,00080.00% June, 2025 $52,457,082$20,126,898
High School Learning Center201601490536Accelerated RepairFinal Audit Approved$1,333,90480.00% $1,036,218 
School for Exceptional Studies201701490537Accelerated RepairFinal Audit Approved$4,500,00080.00% December, 2019 $2,566,666 
Notice on MSBA Project Information
The MSBA updates the project information on the MSBA website on a regular basis; however, due to timing issues or other circumstances, there may be instances where the most up-to-date information does not yet appear. If you have questions or concerns about any of the project information, please contact the MSBA.
The Estimated MSBA Payment Amount Remaining is the maximum amount of funding that the District may still receive from the MSBA for the Project. The actual amount paid by the MSBA may equal an amount less than this estimated amount, as determined by an audit conducted by the MSBA.