School Districts Cities And Towns
 Print this Page
Selected District: Norton
Total Number of Projects: 5 Number of Active Projects: 0

List of Projects for the District are as follows:

School nameMSBAIDProject TypeProject PhaseTotal Project BudgetReimbursement RateEstimated Building Completion DateMSBA Amt Paid(to Date)Estimated MSBA Payment Amt Remaining
Henri A. Yelle201702180060Accelerated RepairCloseout$3,845,94355.63% $1,907,132$190,499
J C Solmonese201202180015Accelerated RepairFinal Audit Approved$1,500,00055.63% $677,706 
J C Solmonese201702180015Accelerated RepairCloseout$2,432,70455.63% $1,156,850$105,826
L G Nourse Elementary201702180010Accelerated RepairCloseout$2,132,28055.63% $1,029,928$115,957
Norton High200902180505Core ProgramFinal Audit Approved$34,589,95564.42% $20,495,176 
Notice on MSBA Project Information
The MSBA updates the project information on the MSBA website on a regular basis; however, due to timing issues or other circumstances, there may be instances where the most up-to-date information does not yet appear. If you have questions or concerns about any of the project information, please contact the MSBA.
The Estimated MSBA Payment Amount Remaining is the maximum amount of funding that the District may still receive from the MSBA for the Project. The actual amount paid by the MSBA may equal an amount less than this estimated amount, as determined by an audit conducted by the MSBA.