Selected District: Wareham
Total Number of Projects: 5 Number of Active Projects: 2

List of Projects for the District are as follows:

School nameMSBAIDProject TypeProject PhaseTotal Project BudgetReimbursement RateEstimated Building Completion DateMSBA Amt Paid(to Date)Estimated MSBA Payment Amt Remaining
John William Decas201503100003Accelerated RepairFinal Audit Approved$2,524,58170.10% November, 2016 $1,082,507 
Wareham Elementary School201503100017Core ProgramCloseout$84,601,93674.98% October, 2021 $46,277,198$5,019,019
Wareham Middle202103100305Accelerated RepairConstruction$8,991,37771.58% $509,622$1,725,225
Wareham Senior High201303100505Accelerated RepairFinal Audit Approved$1,321,92768.00% $732,791 
Wareham Senior High202103100505Accelerated RepairConstruction$2,462,61471.58% $1,027,042$566,726
Notice on MSBA Project Information
The MSBA updates the project information on the MSBA website on a regular basis; however, due to timing issues or other circumstances, there may be instances where the most up-to-date information does not yet appear. If you have questions or concerns about any of the project information, please contact the MSBA.
The Estimated MSBA Payment Amount Remaining is the maximum amount of funding that the District may still receive from the MSBA for the Project. The actual amount paid by the MSBA may equal an amount less than this estimated amount, as determined by an audit conducted by the MSBA.